Weather delay:    
Little or no work done on nice days:    

Due to one of the coldest, rainiest springs in Ottawa, the starting date was delayed three weeks. Duration was promised to be 2-3 weeks. It actually took them 8 weeks. There were several weeks of nice weather where they didn't even bother to show up.

June 2002

Original starting date
Sun Mon Tue Wed Thu Fri Sat
            1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30            

July 2002

Latest promised completion date
(The sod was laid and sometime during the week the arbor was built)
Sun Mon Tue Wed Thu Fri Sat
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      

August 2002

Landscaper found in default of contract
32 days (152%) late on completion date of August 16.